Yes. On MS-Project 2010 go to Levelling Options on the resource tab. Change the field "Look for Overrallocation on a" from Day-to-Day basis to Week-to-Week basis.
The same option is there on prior versions of MS-P IIRC, but you might need to look around for them- It has been a while since I used a prior version.